Project Updates
Rock Creek Parkway
Construction continues on the southbound lanes of Rock Creek Parkway between Enterprise Street and Coalton Road and is expected to last until Nov. 6. Two-way traffic is maintained on the north half of Rock Creek Parkway through the construction area. Please note that the southbound RTD 228A stops at Rock Creek Village/Bell Flatirons and Honey Creek Drive are closed during this closure.
This week (Oct 18 to Oct 24)
Concrete work, including sidewalk repairs and curb and gutter repairs progressed. The new raised crosswalks and islands on the NW and NE corners of the Rock Creek Parkway and Coal Creek Drive intersections are complete. The road subgrade was chemically treated from Coal Ridge to Coalton Road. Honey Creek Drive was paved on Thursday, Oct. 22, and Rock Creek Parkway bottom lift paving was completed on Friday, Oct. 23. The Coalton Road/Rock Creek Parkway intersection was milled on Friday, Oct. 23, in preparation for an asphalt overlay.
Next week (Oct. 25 to 31)
Rock Creek Parkway top lift of asphalt will be placed on Monday, Oct. 26. The Coalton Road/ Rock Creek Parkway Intersection will be overlaid on Tuesday, Oct. 27. There will be partial closures during this work, please expect delays. Striping of Rock Creek Parkway and the intersection will also begin next week.
Have questions or concerns? Contact us! Call us at 720-738-7693 or email pwu@info.superiorcolorado.gov.
Superior Community Center Construction
The facility is closed while crews work to ensure safety and efficiency. Concrete work is complete, including curb and gutter, the west patio, the new ADA parking space, and valley pans for drainage. Asphalt paving began last Wednesday and was completed Thursday. Landscape restoration, striping, and cleaning will occur next week, as well as a punch walk to identify any items that need to be addressed or corrected. Staff will begin to move back into the building later this week. The building will likely open to the public again on or around Nov. 9.
For project details, visit the Town's project webpage or review the Frequently Asked Questions for more information about the closure, temporary program locations, parking, reservations and Community Center services during construction.
Have questions? Call the friendly Guest Service Associates at 303-554-9005 or email tospros@superiorcolorado.gov.
|
North Pool Construction
This renovation will bring significant improvements to the facility, including: a new pool shell and deck, updated bath house, additional shade, a new zero-depth entry wading pool, and more efficient mechanical and sanitation systems.
Demolition of the pool deck and interior of the bathhouse is nearly complete. Xcel will be out to set up temporary power and demolish the existing transformer early this week. Electrical conduit will be placed on the deck and the aquatics subcontractor will be begin forming the pool edge. Utility work will also begin this week.
Tennis courts remain open during construction. Several parking spaces near the entrance to the lot available for tennis players, with a safe pedestrian route to the tennis courts along the construction fencing. Please follow posted signage and construction barriers and avoid entering restricted areas.
The Town will continue to provide weekly project updates throughout the construction phase, including information about project progress, upcoming activities, and any impacts to the surrounding community. Thank you for your patience as we work to transform North Pool into an improved, welcoming facility that the Superior community can enjoy for years to come!
|
South Pool construction
Demolition of the pool and deck is complete and interior demolition of the bathhouse will continue over the next couple of weeks. Excavation for the new pool is underway. Utility work began last week. Work on the pool underdrains is ongoing.
The playground is closed temporarily during concrete demolition. Closures may be intermittent throughout construction based on noise and other safety concerns that would otherwise affect residents utilizing the space. Signage will be posted and the playground re-opened when the area is safe to visit. Please follow posted signage and construction barriers and avoid entering restricted areas
The new pool will include a renovated bathhouse, a larger swimming pool with new play features, including a 25-foot slide and current channel, and a splash pad.
|
|