Weekly Happenings - July 6 to July 12

Published on July 05, 2026

Planning Commission Meeting

July 7 from 6 to 8 p.m.

Town Hall

124 E Coal Creek Drive


Rocky Mountain Metropolitan Airport Advisory Board Meeting

July 8 from 5 to 6 p.m.

Rocky Mountain Metropolitan Airport Terminal Building

11755 Airport Way


Open Mic Night

July 8 from 5:30 to 7:45 p.m.

Superior Community Center

1500 Coalton Road


Open Space Advisory Committee Meeting

July 8 from 6 to 8 p.m.

Superior Community Center

1500 Coalton Road


Advisory Committee for Environmental Sustainability Meeting

July 9 from 5:30 to 7:30 p.m.

Superior Community Center

1500 Coalton Road


Historical Commission Work Session

July 10 from 10 a.m. to noon

Asti Park

101 W. Coal Creek Drive

Grasso Park Interim Historical Museum

122 E. William St.


People clapping along to a Summer Concert.

Summer Concert Series -

High Lonesome

July 11 from 6:30 to 8:15 p.m.

Superior Commons Amphitheater

2130 Creek View Way

 

 

Schedule is subject to change. Visit the Town Calendar for updates.

Town Calendar

Town Meeting Summaries

Superior Youth Leadership Council Meeting

July 1

At the June SYLC meeting, SYLC reviewed the 4th of July volunteer information and due to light attendance, sent out a message to confirm participation. SYLC then sent out another message to see everyone’s availability for a date to do Senior Send Off. The Town briefly talked about the construction happening at the Community Center.

Advisory Committees


Project Updates

Rock Creek Parkway Construction

The north half of Rock Creek Parkway between S. Indiana St. and S. 88th St. remains for roadway reconstruction and underground utility work. Two-way traffic is open on the south half of the road, cyclists are still be requested to utilize the sidewalk through the work zone. Please note the following traffic and RTD impacts for that closure:

  • No through vehicle traffic or bike/pedestrian crossing will be permitted at Coal Creek Drive.
  • No through vehicle traffic will be permitted at S Indiana St.; Cyclists and pedestrians will be able to cross on the West side of the S Indiana St. intersection.
  • 228 Northbound stops on Rock Creek Parkway at S. Indiana St and S. 88th St. will be closed. 

The Town requests that only local traffic use Rock Creek Parkway during construction. All other traffic is encouraged to use Coalton Road and McCaslin Blvd. as detour routes while closures are in effect. Traffic speeds are reduced to 25 MPH and fines doubled in construction zones. For more information of roadway closures for Town capital improvement projects with approximate closure dates, please visit the Town Project website and the Town MAPS webpage. We appreciate your patience and cooperation as we complete these roadway improvements and work to reopen the road as quickly as possible. For questions, please contact Christine Katz at christinek@superiorcolorado.gov.


Concrete Work

Construction continues on the town-wide concrete repairs. This week, crews will be installing the new bike slip ramp on 88th Street near Promenade Drive and wrapping up some final repairs in the Original Town and Down-town areas.


Indiana Street Project

Construction is ongoing with bottom lift paving for phase 1 to be completed this week. Paving was delayed due to issues in the field, but the project is still on schedule to be completed before school starts. Later this week crews plan to move south to complete phase 2 which includes Indiana Street from Mt. Sopris Way to McCaslin Boulevard. Indiana Street will be closed from McCaslin Blvd to just south of Mt. Sopris Way during phase 2.


Alley Stabilization Project

The Original Town alley and roadway stabilization project is ongoing, with stabilization treatment work completed. Next week crews will be installing a chip-seal to further improve the alleys. This work will take approximately 2 days to complete with short-term alley closures occurring during construction.

View Town Projects
Tagged as: