Published on June 29, 2025
Please be advised, roadway repaving is scheduled to start on Sycamore Street between Sagamore and Marshall Road and 76th Street between Coal Creek Drive and Marshall Road starting June 30.
Asphalt milling is schedule for Monday and Tuesday, and paving of Sycamore Street is scheduled for Wednesday and Thursday of next week. During milling, residents can expect temporary lane closures and during paving on Wednesday and Thursday, residents can expect a full roadway closure of Sycamore Street, with traffic being detoured along Marshall Road and 76th Street.
Following paving of Sycamore Street, crews will begin paving 76th Street on July 7. 76th Street will be closed on July 7 and 8 with traffic being detoured down Sycamore Street and Marshall Road during this time.
This schedule is weather dependent and may change. We appreciate your patience and flexibility while this work occurs! Please contact Public Works and Utilities at publicworks@superiorcolorado.gov with questions or concerns.