Rock Creek Parkway construction update

Published on July 14, 2026

Detours in place starting Wednesday, July 15

Starting July 15, Rock Creek Parkway will close between South Indiana Street and Enterprise Street; this includes the closure of South 88th Street up to Shamrock Drive. The closure allows crews to complete corridor improvements before Boulder Valley School District students return to school on Aug. 12.

Emergency services will continue to have access through the construction zone. If evacuation orders are issued, residents will be able to use emergency access points on Lanterns Lane at Promenade Drive, East Weldona Way at 88th Street, and through the construction zone as needed.

Closure details

  • Rock Creek Parkway is closed between South Indiana Street and Enterprise Street in both directions.
  • 88th Street is closed between Shamrock Drive and Rock Creek Parkway in both directions.
Map outlining closures on Rock Creek Parkway and 88th Street in Superior

Map outlining closures on Rock Creek Parkway and 88th Street. Click on the image to enlarge.

Alternative routes

Driving?

  • Rock Creek Parkway Closure: Use Coalton Road, McCaslin Boulevard, or South Indiana Street.
  • 88th Street Closure: Use Coalton Road, McCaslin Boulevard, or West Dillon Road.

Walking or biking?

  • Cross Rock Creek Parkway at South Indiana Street or Enterprise Street.
  • Cross 88th Street at Shamrock Drive.
  • There will be no pedestrian or bike access on sidewalks in the construction zone.

Riding the bus?

  • RTD Route 228 detours on South Indiana Street and Coalton Road. Stops at South Indiana Street, South 88th Street, and Tyler Drive are closed in both directions.

Find more specific closure and detour details on the Town's Streets: Ownership, Snow Removal, and Construction Road Closures map. Select "Rock Creek Parkway Construction: Full Road Closure Starting 7/15 on the left menu bar.

For residents on Reliance Circle, a letter will be provided by July 15 outlining more specific detour options.

Additional Information

  • Single-lane closures have been prioritized throughout construction to limit disruption. Combining the remaining phases into one closure is the fastest path to reopening before school starts.

  • Message boards were updated last week to alert residents of the upcoming closures. Message boards will be updated to show the following along the Rock Creek Parkway corridor:

    Rock Creek Parkway Full Closure
    Indiana to Enterprise 7/15-8/11
    No Access to 88th St

  • An additional message board on 88th Street near Promenade Drive will show:

    88th Street Full Closure
    Shamrock to RCP 7/15-8/11
Find more information on the Town Projects webpage


Thank you for your continued patience and flexibility! If you have additional questions, contact the Public Works and Utilities team.